AuthorsJ. E. Hannay, H. C. Benestad and K. Strand
TitleAgile Uncertainty Assessment – for Benefit Points and Story Points
AfilliationSoftware Engineering
Project(s)Department of IT Management
StatusPublished
Publication TypeJournal Article
Year of Publication2018
JournalIEEE Software
Date Published10/2018
PublisherIEEE Computer Society
ISSN0740-7459
Abstract

Estimates are inherently uncertain, and it’s fair to expect that business value estimates are even more so. By making this uncertainty explicit, you can manage and monitor your agile project according to upper and lower margins of uncertainty. The trick is to instantiate benefit points and story points with values reflecting various scenarios.